DOT to Complete Queens Boulevard Redesign by November: Mayor

Mayor Bill de Blasio announces that fourth and final phase of the Queens Boulevard redesign will be completed by November (Screenshot)

May 13, 2021 By Allie Griffin

The final stretch of the Queens Boulevard redesign will be completed before the end of the year, Mayor Bill de Blasio announced today.

The Department of Transportation (DOT) will finish the fourth and final phase of the redesign in November — about three years behind schedule. Construction, de Blasio said, is expected to begin in July.

The project, which aims to make the boulevard safer for cyclists and pedestrians, has faced continuous delays. It initially faced resistance from Community Board 6 and Council Member Karen Koslowitz and then there were construction delays due to COVID-19.

The plan calls for a revamp of Queens Boulevard from Yellowstone Boulevard to Union Turnpike. It involves the installation of protected bicycle lanes, shortened pedestrian crossings and other traffic safety features. The plan does involve the loss of about 200 parking spots.

The final phase of the Queens Boulevard redesign is scheduled to be completed before the end of 2021. The redesign will go from Yellowstone Boulevard to Union Turnpike in Kew Gardens (Photo: Queens Post)

The overhaul is the final phase of the 7.5-mile redesign of Queens Boulevard, from Sunnyside to Kew Gardens, that began in 2015.

The thoroughfare has been called the “Boulevard of Death” for decades for the notoriously high number of cyclist and pedestrian deaths along it.

Pedestrian injuries decreased by 55 percent and total crashes dipped by 19 percent after the first three phases of the redesign were completed, according to DOT data.

Construction of Phase 4 was supposed to begin in the summer 2018 — but the work was pushed back to summer 2020 and now again to summer 2021.

The final phase has been repeatedly delayed due to opposition from the local community board and Council Member Karen Koslowitz, who said the loss of parking spots would hurt small businesses along the boulevard.

Community Board 6 voted against the plan in 2018, also citing the loss of parking spaces.

Koslowitz put forward an alternative plan in February 2020, which de Blasio agreed to review. Her plan, she said, would save the parking spots. Transit advocates, however, said her plan was not as safe as the DOT’s redesign.

De Blasio said today that the DOT is sticking to its original plan, not Koslowitz’s.

“The council member I think honestly felt that what she was proposing was a better approach for the community and we truly carefully listened to her, thought about, looked at but came to the conclusion that it wasn’t workable and that the original plan was fair,” he said. “I think there were some adjustments made, but it’s based essentially on the original plan.”

Phase 4 of the redesign goes from Yellowstone Boulevard to Union Turnpike. The redesign of the boulevard began in 2015 in Sunnyside (DOT)

De Blasio said that construction was expected to take place last year but COVID-19 struck.

“The last stage, the fourth stage of the Queens Boulevard redesign was getting ready to go and then COVID hit,” de Blasio said. “There was an issue with federal approval, [but] we believe now there’s a much better environment in Washington.”

The plan needs to be reviewed by the State Department of Transportation and the Federal Highway Administration before the DOT can move forward with construction.

De Blasio said that with a different administration in the White House and COVID-19 on the decline, he expects construction to begin in July.

“We need these last approvals… but we are ready to go, and look forward to starting in July and being done in November,” de Blasio said.

Bike and pedestrian safety advocates applauded the announcement, but said it was long overdue.

“We are very pleased that Mayor de Blasio has announced that the next phase of Queens Boulevard will be completed by the end of 2021 — but it should never have taken this long in the first place to transform the Boulevard of Death,” said Danny Harris, Executive Director of Transportation Alternatives.

“New York City is on track to have the second-deadliest year on our streets since Vision Zero began, and Mayor de Blasio and our next mayor must bring the same life-saving street designs for Queens Boulevard to corridors across the five boroughs without delay. This includes extending the project on Queens Boulevard all the way to Hillside Avenue as was initially proposed.”

DOT installing Phase Three of the Queens Boulevard Redesign (DOT)

email the author: news@queenspost.com
No comments yet

Leave a Comment
Reply to this Comment

All comments are subject to moderation before being posted.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Recent News

Rego Park man killed in Bayside chain-reaction crash on Christmas Eve: NYPD

For the second time in less than a week, a motorist was struck and killed after getting out of their vehicle where the Clearview Expressway merges with the Long Island Expressway in Bayside.

The latest fatal collision occurred on the morning of Tuesday, Dec. 24, after a Rego Park man was involved in a crash at around 8:50 a.m. near the northbound ramp of the Clearview Expressway at the westbound entrance to the LIE.

Homeless men charged in deadly 7 train subway brawl in Woodside: DA

Three homeless men were arraigned in Queens Criminal Court on Tuesday and variously charged with felony robbery, attempted gang assault, and assault for allegedly stealing the belongings of a 69-year-old homeless man who was asleep on a Manhattan-bound 7 train in Woodside early Sunday morning.

The victim woke up and tried to regain his property. During the ensuing brawl, the victim fatally stabbed a 37-year-old assailant and slashed a second man. The victim has not been charged in the fatal stabbing. The investigation by the NYPD’s Queens Homicide Squad and members of the 108th Precinct in Long Island City remains ongoing.